RERA: A Silver Lining or Just another Bureaucratic Hurdle for Delayed Possession

Introduction

India’s real estate sector has been highly subject to deceit, fraud, delays, and other malpractices. Earlier, due to the lack of stringent laws and a proper statutory body, many individuals suffered from financial and emotional distress[i]. It became common for homebuyers to pay EMIs for years and still not have a roof over their heads.

With the high need for stringent regulatory bodies and strict laws and regulations, the Real Estate (Regulations and Development) Act of 2016 (“RERA Act”) came into force as a savior and guardian angel safeguarding the rights and interests of homebuyers. However, on the implementation side, it lacks the desired outcomes. This article helps us understand the legislative framework, practical nuances, the role of the relevant regulatory bodies, case studies surrounding the real estate regime, and challenges faced by homebuyers.

The Problem of Delayed Possession

“Delayed Possession occurs when the developer fails to hand over the property to the buyer within the time frame, specified in the Sale Agreement as per RERA Act registered timeline.”

In the case of Anuj Biswas and others V. Kapstone Construction Private Limited[ii], the complainant paid a certain amount to the promoter for 750 Square feet of flat. The flat was located at Rustomjee Urbania Azziano, on the 12th Floor with a bank loan and other resources, the complainant paid 90% of the amount to the promoter. The complainant was informed that he would get possession on December 31, 2015, with 6 months of the grace period, but the date of possession in the registration document was December 2016. Despite repeated attempts by the complainant to contact the developer, they were informed in August 2018 that possession of the flat would only be granted upon the making payment of possession charges, the complainant denied possession and filed a complaint before, the National Consumer Disputes Redressal Commission (NCDRC). The commission relied on the judgment of the case, Emmar MGF Land Limited & Ors. V. Amit Puri[iii], where the court ruled that if the possession is delayed or not delivered at the right time as promised, the buyer has the right to either accept or reject the offer with full repayment of the amount with interest and compensation.

rera
[Image Souces: Shuterstock]

It is a very common cause of real estate matters that can be a result of financial mismanagement, inadequate project planning, or any other malpractice.  It leads to financial and emotional distress for the homebuyers. The developers must provide timely possession to the homebuyers. Delayed Possession has become synonymous with the Indian real estate sector. The excuses given to the homebuyers alleviate the distress faced by the homebuyers as the agreements are heavily skewed in the favor of builders, and homebuyers have limited scope to take action. Stuck in the vicious cycle of financial strain with paying EMIs for years or months, facing corruption at different levels, they end up getting no justice and losing hope.

RERA: A Comprehensive Framework?

The primary objective of the RERA is to bring transparency, accountability, and professionalism.

Mandatory Registration of projects (Section 3)

RERA requires all projects to be registered with RERA authorities making the scope of transparency. All the details of the project like, location, timeline, and other relevant information are recorded. Buyers are legally bound to register. Due to this, all the buyers are on the safer side. But this provision also has some exceptions, where the land is under 500 square meters or there are 8 or less than 8 apartments, the RERA Act will not be applicable for such cases. Then what about the homebuyers dealing in such circumstances? How would they be seeking redressal? This also increases the scope of fraud and other malpractices.

Compensation for Delayed Possession (Section 18)

 Provides two ways for homebuyers to seek redressal

  1. A full refund of the amount given to the homebuyer with the interest
  2. Buyers may opt to retain the property and claim monthly interest

The interest rate is based on the State regulatory body, RERA which is MCLR (Marginal Cost of Funds Based Landing Rate) +2%, and the interest rate is calculated from the due possession date to the actual handover.

This provision empowers housebuyers but in a practical scenario most of the buyers are sleeping over their rights and this often leads to prolonged legal battles. With the high burden on the regulatory body, justice is often delayed. And as we all know “Justice delayed is justice denied”

In the case of Renaissance Infrastructure V. Parth B. Suchak[iv], the complainant had an agreement with the promoter on December 10,, 2009, that stated the transfer of six plots of land and a warehouse to the complainant, as compensation for his retirement from a partnership. As per the agreement, the developer was supposed to deliver the possession by March 9, 2010, with a grace period of 6 months failing which, a certain amount would be paid as compensation. Possession was delayed and the complainant filed a complaint with the Maharashtra Real Estate Regulatory Authority. The Maharashtra RERA ordered the promoter to pay INR 5.04 Crores for 80 months of delay and INR 6,30,000 monthly until the possession was delivered. The appellate authority upheld this decision and directed the promoter to deposit 50% compensation.

  • Escrow Account for Financial Transparency

Section 4 of RERA Act makes it compulsory to deposit 70% of the total fund amount in a separate bank account, this ensures that funds provided by the homebuyers are not misused and also reduces the risk of mismanagement but it does not eliminate all avenues for developers to exploit loopholes.

  • Grievance Redressal Mechanisms

Homebuyers can complain against the buyer with the help of the Online Portal of RERA State Authority. But the main problem here is, does every individual is capable of doing so? In a country where more than 60% of the population is living in rural areas with no literacy or education. Online Dispute Resolution (ODR), is not truly going to work. While RERA is in its baby stages, most of the people are unaware of it. Although, with the help of law professionals this would work for all individuals but also not all individuals can afford this way to seek redressal.

  • Structural Defects

If there are structural defects on the property or house builders will be liable to rectify the defects within 30 days for consecutive 5 years of the possession, or else the developer will be compelled to pay the compensation and interest to the homebuyer.

Challenges of RERA Implementation:

  • Awareness Deficit Among Homebuyers

One of the biggest problems in the implementation of the RERA Act is that people are not aware and mostly sleep over their rights. This raises a concern regarding the role of government in disseminating information to the public at large. The statute is protecting the poor, and that is true. However, for poor to know of the protection, he shall know.

  • Fragmented and Diluted Implementation

RERA’s decentralized implementation across the states has led to a lack of uniformity in implementation. Due to the constant pressure from the real estate lobbies, many states have diluted the provisions of the statute and also excluded ongoing projects.

  • Toothless Penalties

With different states having different authorities, they follow different interpretation mechanisms. Penalties on paper are stringent but the ground reality is much different. A major role of corruption is also observed where people having connections and some power misuse it. Especially in the Indian real estate sector mafias, criminals are often involved which is another reason for injustice to the innocent.

  • Delayed Justice Defeat Purpose

RERA Act promises swift dispute resolution within 60 days, but in reality, this promise is just a wish. With all the homebuyers suffering, they face another phase of suffering which is delayed justice.

  • Digital Shortcomings

While RERA emphasizes transparency through online portals, giving all the details, most state websites are not properly workable. Many times there are plenty of glitches, missing data, and worst cases wrong data are there. The lack of technology reflects how poorly the act is implemented.

Conclusion

RERA Act and the authorities formed under it have undoubtedly brought changes in the real estate ecosystem of India. The provisions provided for delayed possession are well-introduced and empower the homebuyers, protecting their interests and rights. However, the darker side of the said act is seen while implementing it. While the state’s negligence is a matter of concern, it’s the people who are sleeping over rights. While RERA offers hope to the poor but does not equally scare the developer for his misconduct and malpractices. As it is still on the stage of development, the need to make it more stringent is realized also by providing information to all the people, especially to the people of rural areas, who have no access to the internet and technology, a committee should be set up to deal with those individuals is also required. The government must address all these systematic challenges and ensure that the RERA act delivers on its promise. Only then can RERA Act[v] transform from being a partial savior to a robust protector of homebuyer’s rights.

Author: Akshat Gangwani, in case of any queries please contact/write back to us via email to chhavi@khuranaandkhurana.com or at Khurana & Khurana, Advocates and IP Attorney.

References

[i] Ministry of Housing and Urban Affairs

[ii] Consumer case no. 2760 of 2018

[iii] [II (2015) CPJ 568 NC]

[iv]  MANU/RT/0001/2020

[v] Real Estate (Regulation and Development) Act, 2016

Leave a Reply

Categories

Archives

  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • August 2024
  • July 2024
  • June 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • December 2019
  • November 2019
  • October 2019
  • September 2019
  • August 2019
  • July 2019
  • June 2019
  • May 2019
  • April 2019
  • March 2019
  • February 2019
  • January 2019
  • December 2018
  • November 2018
  • October 2018
  • September 2018
  • August 2018
  • July 2018
  • June 2018
  • May 2018
  • April 2018
  • March 2018
  • February 2018
  • January 2018
  • December 2017
  • November 2017
  • September 2017
  • August 2017
  • July 2017
  • June 2017
  • May 2017
  • April 2017
  • March 2017
  • February 2017
  • January 2017
  • December 2016
  • November 2016
  • October 2016
  • September 2016
  • August 2016
  • July 2016
  • June 2016
  • May 2016
  • April 2016
  • March 2016
  • February 2016
  • January 2016
  • December 2015
  • November 2015
  • October 2015
  • September 2015
  • August 2015
  • July 2015
  • June 2015
  • May 2015
  • April 2015
  • March 2015
  • February 2015
  • January 2015
  • December 2014
  • November 2014
  • October 2014
  • September 2014
  • August 2014
  • July 2014
  • May 2014
  • April 2014
  • March 2014
  • February 2014
  • January 2014
  • December 2013
  • November 2013
  • October 2013
  • September 2013
  • August 2013
  • July 2013
  • June 2013
  • May 2013
  • April 2013
  • March 2013
  • February 2013
  • January 2013
  • December 2012
  • November 2012
  • September 2012
  • August 2012
  • July 2012
  • June 2012
  • May 2012
  • April 2012
  • March 2012
  • February 2012
  • January 2012
  • December 2011
  • November 2011
  • October 2011
  • September 2011
  • August 2011
  • July 2011
  • June 2011
  • May 2011
  • April 2011
  • February 2011
  • January 2011
  • December 2010
  • September 2010
  • July 2010
  • June 2010
  • May 2010
  • April 2010