Section 74 of ICA And Non-Compete Agreements: Examining Indian Court’s Approach

INTRODUCTION

The Indian Contract Act, 1872, primarily establishes the regulations concerning liquidated damages under section 74. In essence, it states that parties may specify in the contract itself an amount that will be paid by the party in default to the other party in event of a breach of contract. The party seeking damages for the violation of contract must be entitled to a reasonable damages.

If there is a breach of contract, the liquidated damages clause provides for the payment of a predetermined amount. This blog looks at how Indian courts have interpreted the contracts’ liquidated damages clauses. In addition, it addresses the particular situation of non-compete agreements and studies legal options that either party may pursue in order to support its position,

SCOPE OF SECTION 74

The Court, in the case of FATEH CHAND V. BAL KISHAN DAS clarified that section 74 deals with damages in two categories of instances when discussing its scope:

First, whether the sum to be paid in the case of a contract violation has been predetermined.

For instance- Party A contracts with party B to pay a sum of Rs. 1,000, if he fails to pay B Rs. 500 on a given day. A fail to pay B Rs. 500 on that day. B is entitled to recover from A such compensation, not exceeding Rs. 1,000, as the Court considers reasonable.

Secondly, in cases when any additional penalty clauses may be included in the contract.

 QUANTUM OF LIQUIDATED DAMAGES

If a party properly rescinds a contract, it may be entitled to indemnification for any losses or damages resulting from non-performance under this clause.

The Supreme Court of India ruled that, in relation to the amount of liquidated damage, the parties proposed amount may be taken into consideration as a measure of reasonable compensation if it is thought to be a true pre-estimate (but not if the amount is intended to be penalized). This is true even in cases where the court is unable to evaluate the amount of compensation. However, as indirect consequential losses are not quantified in the contracts, they may also be covered by the aforementioned Supreme Court approach.

Concerning the quantity of liquidated damages, it is a well- established legal principle that in order to quantify damages in monetary terms, the party making the claim must provide evidence of the loss incurred. In addition, a significant factor in that determines damage liability is the principle of causation and the efforts made by the parties in minimizing such losses.

[Image Sources: Shutterstock]

Contract Act

In the case of MAULA BUX V. UNION OF INDIA, the Supreme Court ruled that, in cases where the court of appeals decides that compensation can be determined in conformity with established guidelines under the specific facts and circumstances, the claimant may be required to present proof of the real loss resulting from the breach.

We can say that the general rule governing a non-defaulting party’s ability to seek consequential damages is that the non-defaulting party may only recover or assert any portion of the loss resulting from the defaulting party’s infringement that was reasonably foreseeable at the time the contract was executed. The knowledge that each party possesses and shares will determine the extent of the reasonably foreseeable loss or damage, among other things.

The parties may stipulate in a contract that, in the event of a breach, no money will be paid out except for the refunds of sums paid and that the parties agree that such a stipulation is enforceable. The parties can also define unique and specific obligations for themselves, including how much damages are awarded for infringement.

NON-COMPETE CLAUSE

A non-compete clause is a provision in a contract that states, when the contract expires or is terminated, that a party shall not engage into a new agreement with any other business. These terms specify the geographic area, the market, and/or the duration that the party must wait to work with another party. These sorts of clauses typically specify how much a party will be entitled to in the event that the other party violates the same.

Currently, in a lawsuit, one of the two parties would be convicted for breaking the terms of the agreement, and the other would have to deal with the fallout. The former would undoubtedly be inclined to argue that the contract’s damages are not real in order to avoid paying any damages at all or to pay a reduced amount. The latter, however, would contend that the predetermined damages in the clause are legitimate and reasonable and would want them to remain as they are.

According to the Kailash Nath case ratio, the party that violates the contract may argue that the amount of liquidated damages is excessive and that a much smaller amount should be awarded as damages as the amount is only the ceiling limit and is not legally enforceable. The same would rely on the case’s particular facts and circumstances. One possible response is that the non-compete provision cannot, in theory, be applied because the new entity’s business model differs from the old entity’s (the entity that was violated).

Alternatively, the party that was harmed by the breach of contract and is claiming a legitimate amount of damages can support their position by first demonstrating that the non-compete agreement was a goodwill transaction and then presenting prior financial data. Given the prior entity’s goodwill in that business model, it makes sense that any new entity operating under the same model would most likely generate income equal to the consistent revenue generated by the previous entity. Liquidated damages specified in the non-compete agreement will therefore be proven to be fair and genuine and will not subject to diminution if the court is convinced that the new firm is generating the same revenue as the previous entity.

CONCLUSION

If the court believes that the agreed damages are reasonable, it will award the predetermined damages specified in the contract. If it isn’t, though, the court will step in and grant the appropriate amount of damages, using the maximum damages specified in the contract as a guideline. In light of this, should a contract be broken, the parties may first dispute whether or not the damages are justifiable and authentic. In addition, the party whose non-compete was violated may utilize its financial records to support its claim for damages under the terms of the agreement.

Author: Aniya vijayvergiya , in case of any queries please contact/write back to us via email to chhavi@khuranaandkhurana.com or at  Khurana & Khurana, Advocates and IP Attorney.

Leave a Reply

Categories

Archives

  • November 2024
  • October 2024
  • September 2024
  • August 2024
  • July 2024
  • June 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • December 2019
  • November 2019
  • October 2019
  • September 2019
  • August 2019
  • July 2019
  • June 2019
  • May 2019
  • April 2019
  • March 2019
  • February 2019
  • January 2019
  • December 2018
  • November 2018
  • October 2018
  • September 2018
  • August 2018
  • July 2018
  • June 2018
  • May 2018
  • April 2018
  • March 2018
  • February 2018
  • January 2018
  • December 2017
  • November 2017
  • September 2017
  • August 2017
  • July 2017
  • June 2017
  • May 2017
  • April 2017
  • March 2017
  • February 2017
  • January 2017
  • December 2016
  • November 2016
  • October 2016
  • September 2016
  • August 2016
  • July 2016
  • June 2016
  • May 2016
  • April 2016
  • March 2016
  • February 2016
  • January 2016
  • December 2015
  • November 2015
  • October 2015
  • September 2015
  • August 2015
  • July 2015
  • June 2015
  • May 2015
  • April 2015
  • March 2015
  • February 2015
  • January 2015
  • December 2014
  • November 2014
  • October 2014
  • September 2014
  • August 2014
  • July 2014
  • May 2014
  • April 2014
  • March 2014
  • February 2014
  • January 2014
  • December 2013
  • November 2013
  • October 2013
  • September 2013
  • August 2013
  • July 2013
  • June 2013
  • May 2013
  • April 2013
  • March 2013
  • February 2013
  • January 2013
  • December 2012
  • November 2012
  • September 2012
  • August 2012
  • July 2012
  • June 2012
  • May 2012
  • April 2012
  • March 2012
  • February 2012
  • January 2012
  • December 2011
  • November 2011
  • October 2011
  • September 2011
  • August 2011
  • July 2011
  • June 2011
  • May 2011
  • April 2011
  • February 2011
  • January 2011
  • December 2010
  • September 2010
  • July 2010
  • June 2010
  • May 2010
  • April 2010